ID
Name
TBEA Xinjiang New Energy CO
Country of registration/origin
China
Relationship
Beneficiary company
Investment type
Debt financing
Loan amount
701 880 000
$
Comment
Provides soft loan to Mafeteng Ramarothole Solar PV .
Phase I (30MW) of the Mafeteng Ramarothole Solar PV Park is financed by a soft loan from the EXIM Bank of China totaling USD 70.188 million
ID
Name
Cambodian Tatay Hydropower Ltd. (CTHL)
Country of registration/origin
Cambodia
Classification
Private company
Relationship
Beneficiary company
Investment type
Debt financing
Loan amount
540 000 000
$
Loan date
2015
Comment
Financed under a USD $540 million loan from the China Export–Import Bank (EXIM Bank)
ID
Name
Pak Lay Power Company Limited
Country of registration/origin
Lao PDR
Classification
Private company
Relationship
Beneficiary company
Investment type
Debt financing
Loan amount
1 700 000 000
$
Loan date
2017-01-17
Comment
China Eximbank pledges $1.7 billion loan for 1320MW Pak Lay Hydropower Project
ID
Name
Lao Kaiyuan Mining Sole Co. Ltd
Country of registration/origin
Lao PDR
Classification
Private company
Relationship
Beneficiary company
Investment type
Debt financing
Loan amount
20 000 000
$
Comment
This project is linked to a $20 million loan pledge from China Eximbank (captured in Record ID#64227) for the Lao Kaiyuan Potash Mine Project.
ID
Name
Lao–China Joint Venture Investment Company Limited (LCJV)
Country of registration/origin
Lao PDR
Classification
Private company
Relationship
Beneficiary company
Investment type
Debt financing
Loan amount
620 000 000
Loan date
2013
Comment
In 2013, the Export–Import Bank of China (China Eximbank) provided YOIC with a loan of 200 million RMB to cover pre-investment expenses related to the SDZ. China Eximbank went on to provide another loan, of 420 million RMB, for the project, with the first instalment issued by the bank’s Yunnan branch on 12 May 2015.