Deal #9818 Version 91993 Version 93494
Intended size
300 ha
Size under contract (leased or purchased area)
  • [current] 300 ha
  • [2013, current] 300 ha
Size in operation (production)
  • [current] 300 ha
  • [2014, current] 300 ha
Comment on land area
Letsatsi Power Solar PV Park is a ground-mounted solar project which is spread over an area of 300 hectare
Letsatsi Power Solar PV Park is a ground-mounted solar project which is spread over an area of 300 hectares.
Carbon offset project
Yes
Nature of the deal
Lease
Implementation status
  • [2013] Project not started
  • [2014-05, current] In operation (production)
  • [2013] Startup phase (no production)
  • [2014-05, current] In operation (production)
Comment on jobs created (total)
creates permanent and seasonal job
creates permanent and seasonal job
Electricity generation
  • [current] Solar (Photovoltaic)
    Currently installed capacity: 75 MW
  • [2020, current] Solar (Photovoltaic) 300 ha
    Currently installed capacity: 75 MW
Carbon sequestration/offsetting
  • [2013, current] Solar park ( 300 ha)
    Estimated emission reduction/removal during project lifetime: 134690 tCO2e
    Estimated annual emission reduction/removal: 80907 tCO2e
    Certification standard: Yes
    Name of certification standard/mechanism: Clean Development Mechanism (CDM)
    ID of certification standard/mechanism: 7167
Comment on carbon sequestration/offsetting
10 years of crediting period.
Fully updated
No
Yes

Location #eDaDPC06

Spatial accuracy level
Exact location
Coordinates
Facility name
Jedwater Farm
Letsatsi Solar Plant

Data source #ARlFLtiN

File

Data source #6_4O55Oq

File
Type
Government sources
Url
Keep PDF not public
No
Publication title
COMPONENT PROJECT ACTIVITY DESIGN DOCUMENT FORM (F-CDM-CPA-DD)
Date
2013
Organisation
UNFCCC/CCNUCC