Comment on implementation status | It was expected that construction will take place between 2018 and 2019. The first wind turbine was assembled on 18th November 2019 Now (2021) the project is in the process of significant expansion and development. The planned design capacity is 246 MW. | It was expected that construction will take place between 2018 and 2019. The first wind turbine was assembled on 18th November 2019. In 2021 the project is in the process of significant expansion and development. The planned design capacity is 246 MW.
The wind farm is currently located on the occupied territory. Most of the windmills were destroyed after Russia's full-scale invasion of Ukraine began. |
Employment | ||
Investor info | ||
Local communities / indigenous peoples | ||
Former use | ||
Produce info | ||
Electricity generation |
| |
Comment on electricity generation | As of 2022, some wind turbines have been destroyed due to Russia's war in Ukraine. | |
Water | ||
Gender-related info | ||
Overall comment | ||
Meta | ||
Locations | ||
Location #eQpJiEkV | ||
areas | unknown field: location.areas | unknown field: location.areas |
Location #2j0SwQV6 | ||
areas | unknown field: location.areas | |
Location #Y4Rxx1bp | ||
areas | unknown field: location.areas | |
Spatial accuracy level | Approximate location | |
Location | Першокостянтинівка, Kherson Oblast, Ukraine | |
Point | Lat: 46.24894 Lng: 33.66994 | |
Description | area under wind farm | |
Data sources | ||
Data source #hasAMioQ | ||
Date | 2018 | 2018-05-22 |
Data source #mQag_pdN | ||
File | ||
Date | 2024-03-04 | |
Comment on data source | Information about the wind farm.
The date of access to the website is indicated | |
Data source #3mh3k4dL | ||
Url | ||
Data source #TEKhVGHq | ||
File | ||
Date | 2020-01-23 | |
Data source #JQGMfo9d | ||
File | ||
Date | 2024-03-04 | |
Comment on data source | Operating company profile attained from the aggregator of national registers | Operating company profile attained from the aggregator of national registers
Date of access to the website is indicated |
Data source #xImlmNlV | ||
Date | 2021-11-15 | |
Comment on data source | Investor company profile | Investor company profile
Date of access to the website is indicated |
Data source #9FeIkpe- | ||
File | ||
Date | 2024-03-04 | |
Comment on data source | Investor's main page | Investor's main page
Date of access to the website is indicated |
Data source #s0C9JBlZ | ||
Date | 2021-11-15 | |
Comment on data source | Project profile | Project profile
Page is no longer available |
Data source #2KVIoz1o | ||
Date | 2018 | 2018-11-29 |
Data source #fUL9Msxh | ||
File | ||
Date | 2019-02-07 | |
Data source #e5SNaQNh | ||
File | ||
Date | 2021 | 2021-10-15 |
Data source #48e8osGz | ||
File | ||
Type | Other | |
Url | ||
Keep PDF not public | No | |
Date | 2024-03-05 | |
Comment on data source | Information about land plots attained from the aggregator of national registers
Date of access to the website is indicated | |
Data source #JlzLPdX9 | ||
File | ||
Type | Government sources | |
Url | ||
Keep PDF not public | No | |
Date | 2019-07-09 | |
Comment on data source | On issuance of the Electricity Generation Licence to SYVASHENERGOPROM LLC | |
Data source #ZL7XNfBy | ||
File | ||
Type | Media report | |
Url | ||
Keep PDF not public | No | |
Date | 2022-05-25 | |
Comment on data source | Wind farm damaged as a result of hostilities in Ukraine | |