Deal #9845
South Africa
Created at
2023-02-03
Last update
2024-08-23
Land area
Size under contract (leased or purchased area)
- [current] 84.98 ha
Intention of investment
Intention of investment
- [current] Solar park (84.98 ha)
Comment on intention of investment
Electricity supply through solar energy
Carbon offset project
Carbon offset project
No
Negotiation status
Negotiation status
- [current] Concluded (Contract signed)
Implementation status
Implementation status
- [2014] Startup phase (no production)
- [2017-09, current] In operation (production)
Comment on implementation status
Construction began 2014. The plant commenced its commercial operations in September 2017
Contract farming
Contract farming
No