Deal #9745

Ukraine
Created at
2022-12-09
Last update
2024-02-26
Last full update
2024-02-20

Land area

Size under contract (leased or purchased area)
  • [2012, current] 158 ha
Comment on land area
The exact information about the area used for the wind power plant was not found. Based on the news about the geodetic works for the construction of the Novoazovsk wind park and the creation of plans with the areas of 64 and 94 hectares, we indicated the approximate area of the land plots used.

Intention of investment

Intention of investment
  • [2011, current] Wind farm

Nature of the deal

Nature of the deal
Lease
Comment on nature of the deal
Lease of 65 land plots for the construction and use for the Novoazovskaya wind farm.

Negotiation status

Negotiation status
  • [2011-12, current] Concluded (Contract signed)
Comment on negotiation status
In December 2011, the agreement with the bank was signed and the work on the preparation of the loan disbursement started.

Implementation status

Implementation status
  • [2011] Startup phase (no production)
  • [2012-03] In operation (production)
  • [2014, current] Project abandoned
Comment on implementation status
In March 2012, the first stage of the Novoazovskiy wind park near the village of Bezimenne, Donetsk region, was completed. Since the beginning of the war in 2014, the territory of Donetsk region became occupied and inaccessible for Ukraine. Therefore, the Novoazovsk wind park can not be controlled by either Ukrainian or foreign investors.