Please note: you are viewing an old version of this deal. The current version can be found here: Deal #9733
Deal #9733 Version #90227
South Africa
Created at
2022-12-06
Last update
2023-04-26
Last full update
2024-09-13
Land area
Intended size
125 ha
Size under contract (leased or purchased area)
- [current] 125 ha
Comment on land area
The 125 hectare, 86MW
Intention of investment
Intention of investment
- [current] Renewable energy unspecified (124.97 ha)
Comment on intention of investment
Sonnedix develops, builds, and operates renewable energy projects for the long-term, with a focus on providing green, affordable electricity to our customers
Negotiation status
Negotiation status
- [current] Concluded (Contract signed)
Implementation status
Implementation status
- [2016-07-22, current] In operation (production)
- [2015] Startup phase (no production)
Comment on implementation status
In the Northern Cape it officially started commercial operation on Friday 22 July, 2016. Construction was completed after only 17 months.
“The project was completed in due time as per the schedule and is now fully operational