Deal #9544 | Version 88330 | Version 93314 |
---|---|---|
General info | ||
Intended size | 228โฏ687 ha | 343.15 ha |
Size under contract (leased or purchased area) |
| |
Comment on land area | 34498 of 228687 or 15% were taken from the total intended size | By combining the size of land plots on the cadastral map, the total area is larger than planned. There is land take, totaling 45 ha, required for infrastructure related the Project, primarily for the transmission line, including land for poles and anchor towers. |
Intention of investment |
|
|
Comment on intention of investment | Twenty-eight 105m high towers of Mingyang turbines (16 of 3.2MW and 12 of 4.0MW output power) will hold 156m diameter blades that will rotate with the wind from 2 to 25 m/s at a rotational speed range of 10-20 rpm. | Twenty-eight 105m high towers of Mingyang turbines (16 of 3.2MW and 12 of 4.0MW output power) will hold 156m diameter blades that will rotate with the wind from 2 to 25 m/s at a rotational speed range of 10-20 rpm. The Project is divided into several companies, each assigned to a separate sub-project: Borey Energo LLP (Borey) โ 20 wind turbines; Energo Trust LLP (Energo Trust) โ 10 wind turbines; Sofievskaya Wind Power Plant LLP (Sofievskaya) โ 8 wind turbines; Arkalyk Wind Power Plant LL (Arkalyk) โ 3 wind turbines, and Jasyl Jel Energy (JJE) โ 3 wind turbines. |
Comment on nature of the deal | 13 lease agreements | 13 lease agreements. Land lease was approved for a period of 49 years. Cadastral numbers of land plots: 01005008424, 01005008425,
01005008426, 01005008427, 01005008429, 01005008430, 01005008431, 01005047220, 01005047227, 01005047226, 01005010347, 01005010341, 01005011045 |
Negotiation status |
| |
Implementation status |
|
|
Comment on implementation status | To determine the local conditions and areaโs vulnerability a survey was carried out from March 16, 2020 to March 3, 2021. Construction of the wind farm started in May 2022. | |
Employment | ||
Investor info | ||
Operating company | ||
Name of investment project | Borey wind power plant (WPP) | |
Comment on investment chain | The provision of a senior loan of up to US$ 45.6 million equivalent (in US$ and KZT) to Borey Wind LLP and The provision of a senior secured loan of up to US$ 22 million equivalent (in US$ and KZT) to Energo Trust LLP. | |
Local communities / indigenous peoples | ||
Community consultation | Limited consultation | |
Comment on consultation of local community | In February, 2020 the Arshaly District Council held a meeting in Bulaksay, which was advertised on the village noticeboard, for attendees to review the allocation of land required for the 156MW extension. The meeting was chaired by the Bulaksay rural area council, with the head of the Arshaly District Council Entrepreneurship Department and attended by 19 village residents. In November, 2020 the Arshaly District Council, along with representatives from the project, held a meeting with residents from Saryoba Station to explain the Project also. There was also an instance where the Councillor had requested a number of crossings over the trenching work to allow for agricultural machinery and animals to cross safely. The Client worked with six herders to determine where best to situate these crossings to meet the herders needs. | |
Community reaction | Consent | |
Comment on community reaction | During this meeting the villagers approved the land allocation for the Project, which was documented and included as part of the application for the land lease. | |
Comment on promised benefits for local communities | If the water is taken from the Bulaksay or Saryoba station water supplies, shortages during the peak time usage may arise. To prevent this, the Company will repair the village pipework and pumps. | |
Former use | ||
Former land owner | State, Private (smallholders) | |
Comment on former land owner | One source indicates that one of the land plots was in state ownership. | |
Produce info | ||
Electricity generation |
| |
Comment on electricity generation | The Project is divided into several companies, each assigned to a separate sub-project: Borey Energo LLP (Borey) โ 20 wind turbines; Energo Trust LLP (Energo Trust) โ 10 wind turbines; Sofievskaya Wind Power Plant LLP (Sofievskaya) โ 8 wind turbines; Arkalyk Wind Power Plant LL (Arkalyk) โ 3 wind turbines, and Jasyl Jel Energy (JJE) โ 3 wind turbines. | |
Water | ||
Gender-related info | ||
Overall comment | ||
Overall comment | Added location, Investor info, Intention of investment, Implementation status,Number of total jobs created, Promised benefits for local communities, Water extraction envisaged, Land area, Nature of the deal, Former land cover, data source | |
Meta | ||
Locations | ||
Location #mffvdk-L | ||
Location | Arshaly, Kazakhstan | Bulaksay, Kazakhstan |
Point | Lat: 52.72275 Lng: 61.14022 | Lat: 51.29299 Lng: 72.09259 |
Location #3YB8_UJ1 | ||
areas | unknown field: location.areas | |
Spatial accuracy level | Exact location | |
Location | ะะก ะะพัะตะน ะญะฝะตัะณะพ Borey Energo, ะัะปะฐะบัะฐะน (ะะพะฒะพะฒะปะฐะดะธะผะธัะพะฒะบะฐ), ะะฐะทะฐั
ััะฐะฝ | |
Point | Lat: 51.26729 Lng: 72.07168 | |
Data sources | ||
Data source #X4TIbtwI | ||
Date | 2021 | |
Comment on data source | Non-Technical Summary (EN) | |
Data source #4Lt-WdRt | ||
File | ||
Type | Other | |
Url | ||
Keep PDF not public | No | |
Publication title | Kazakhstan: Zhanatas 100 MW Wind Power Plant | |
Comment on data source | former use, mn | |
Data source #h67eGwna | ||
File | ||
Type | Research Paper / Policy Report | |
Keep PDF not public | No | |
Date | 2023-12 | |
Comment on data source | Project Non-Technical Summary for Akmola Wind Farm, December 2023 | |
Data source #4iZMkkCz | ||
File | ||
Type | Other | |
Url | ||
Keep PDF not public | No | |
Date | 2023-12-01 | |
Organisation | EBRD | |
Data source #YCw_vYWT | ||
File | ||
Type | Other | |
Url | ||
Keep PDF not public | No | |
Date | 2023-12-12 | |
Organisation | EBRD | |
Data source #U-bX2eOJ | ||
File | ||
Type | Government sources | |
Url | ||
Keep PDF not public | No | |
Date | 2024-06-20 | |
Comment on data source | Cadastral map of Kazakhstan. Information about leased land plots, their size and location. The date of access to the website is indicated | |
Data source #st7T_gpu | ||
File | ||
Type | Other | |
Url | ||
Keep PDF not public | No | |
Date | 2024-06-20 | |
Comment on data source | Google Map. Location of Wind farm | |
Data source #lRmAQtAF | ||
File | ||
Type | Media report | |
Url | ||
Keep PDF not public | No | |
Date | 2022-11-29 | |
Data source #lCsJ_yOU | ||
File | ||
Type | Media report | |
Url | ||
Keep PDF not public | No | |
Date | 2023-10-10 | |
Data source #2CgPgA7d | ||
File | ||
Type | Media report | |
Keep PDF not public | No | |
Date | 2024-01 | |
Contracts | ||
Contract #P6vu_XLJ | ||
Duration of the agreement | 49 years | |
Comment on contract | Cadastral numbers of land plots: 01005008424, 01005008425, 01005008426, 01005008427, 01005008429, 01005008430, 01005008431, 01005047220, 01005047227, 01005047226, 01005010347, 01005010341, 01005011045 |