Deal #9543
Kazakhstan
Created at
2022-07-18
Last update
2024-05-09
Last full update
2024-05-08
Land area
Intended size
300 ha
Size under contract (leased or purchased area)
- [current] 150 ha
Intention of investment
Intention of investment
- [2015, current] Solar park
Comment on intention of investment
50 MW Solar photovoltaic power plant Burnoye-1 (SPP1)
Negotiation status
Negotiation status
- [2013] Intended (Expression of interest)
- [2014-04, current] Concluded (Contract signed)
Comment on negotiation status
Burnoye Solar-1 LLP was established in April 2014.
Implementation status
Implementation status
- [2013] Startup phase (no production)
- [2015-04, current] In operation (production)
Comment on implementation status
Project development and planning started in 2013. In May 2014, construction of the SPP began.