Deal #9498

Myanmar
Created at
2022-06-23
Last update
2023-03-10
Last full update
2023-03-10

Land area

Intended size
6 500 ha
Comment on land area
The project has a 409km onshore gas pipeline operated by Total in the Myanmar territory, in addition to 240km in Thailand owned by PTT Plc. The offshore pipeline of the project is 65km on land, covering the point from where the subsea gas pipeline emerges onto dry land at the Daminseik and the Thai frontier.

Intention of investment

Intention of investment
  • [1998, current] Oil / Gas extraction

Negotiation status

Negotiation status
  • [2022-07-20, current] Concluded (Change of ownership)
  • [1980] Intended (Expression of interest)
  • [1994] Concluded (Contract signed)
Comment on negotiation status
As of January 2022, TotalEnergies has announced that they will withdraw from the Yadana project as the operator and joint venture partner,[8] and PTT Exploration and Production Public Company Limited (PTTEP) will take over. The nomination of PTTEP as the new operator has been appointed by the remaining partners in this project. The operatorship transfer is expected to be completed on July 20, 2022.

Implementation status

Implementation status
  • [2018] In operation (production)
  • [2022, current] In operation (production)
  • [1994] Startup phase (no production)
Comment on implementation status
company website reports its in operation in 2022