Deal #9448
Ghana
Created at
2022-05-21
Last update
2024-10-28
Land area
Intended size
6 070 ha
Intention of investment
Intention of investment
- [current] Wind farm (6 070 ha)
Carbon offset project
Carbon offset project
No
Nature of the deal
Nature of the deal
Lease
Comment on nature of the deal
The Land Lease Agreement for the Ayitepa Wind Farm involves a legal contract between Upwind Ayitepa Ltd., the project's special purpose vehicle (SPV) in Ghana, and the Government of Ghana.
Negotiation status
Negotiation status
- [current] Intended (Under negotiation)
Comment on negotiation status
The 225 MW Ayitepa Wind Project in Ghana is not yet operational; it has all necessary permits but is still awaiting cabinet and parliamentary approval to begin construction.
Implementation status
Implementation status
- [2024, current] Project not started