Land area

Size under contract (leased or purchased area)
  • [2014, current] 180 ha
Size in operation (production)
  • [2018-06, current] 180 ha
Comment on land area
The total area of the project footprint, which includes roads, turbine platforms, substation and ancillary facilities amounts to about 180 hectares

Intention of investment

Intention of investment
  • [2014, current] Wind farm (180 ha)
Comment on intention of investment
Onshore wind power project.

Carbon offset project

Carbon offset project
No

Nature of the deal

Nature of the deal
Lease

Negotiation status

Negotiation status
  • [2014, current] Concluded (Contract signed)

Implementation status

Implementation status
  • [2018-06, current] In operation (production)
Comment on implementation status
It has been developed in single phase. Post completion of construction, the project got commissioned in June 2018.

Contract farming

Contract farming
No