Please note: you are viewing an old version of this deal. The current version can be found here: Deal #8767

Deal #8767 Version #91920

Egypt, Arab Rep.
Created at
2021-06-08
Last update
2024-02-23

Detailed electricity generation information

Electricity generation
  • [current] On-shore wind turbines
    Number of turbines: 96 Intended capacity: 250 MW
Comment on electricity generation
The project consists of 96 Siemens-Gamesa 2.6 MW turbines with a tower hub height of 63 m and rotor diameter of 120 m, a substation and a network of site access roads

Use of produce

Has domestic use
Yes
Domestic use
100 %
Comment on use of produce
Feed power into the domestic electricity grid