Please note: you are viewing an old version of this deal. The current version can be found here: Deal #8345
Deal #8345 Version #83147
Lao PDR
Created at
2020-09-22
Last update
2021-11-11
Last full update
2022-08-17
Land area
Size in operation (production)
- [current] 2234.0 ha
Comment on land area
Phase 1:
Nam Ou 2 HPP reservoir area: 2,215,900 hectares
Nam Ou 5 HPP reservoir area: 1,027,000 hectares
Nam Ou 6 HPP reservoir area: 548,000 hectares and is estimated to result to loss of 2,234 hectares of land due to inundation (2,000 hectares) and 234 hectares (building area).
Phase 2:
Nam Ou 1 HPP
Nam Ou 3 HPP
Nam Ou 4 HPP
Nam Ou 7 HPP
Intention of investment
Intention of investment
- [current] Renewable energy unspecified
Comment on intention of investment
The cascade units are being developed in two phases with a cumulative capacity of 1,272 MW.
Nam Ou 2 installed capacity: 120 MW
Nam Ou 5 installed capacity: 240 MW
Nam Ou 6 installed capacity: 180 MW
Nam Ou 1 installed capacity: 180MW
Nam Ou 3 installed capacity: 210MW
Nam Ou 4 installed capacity: 132MW
Nam Ou 7 installed capacity: 210MW
Nature of the deal
Nature of the deal
Concession
Comment on nature of the deal
25-year build, operate and transfer (BOT) agreement
Negotiation status
Negotiation status
- [2011-04-01, current] Concluded (Contract signed)
Implementation status
Implementation status
- [2012-10-01] Startup phase (no production)
- [2017-01-01] In operation (production)
- [2019-12-01, current] In operation (production)
Comment on implementation status
Phase one of the project consisting of three units with a total installed capacity of 540MW was commissioned in January 2017. The construction work on phase two, which comprises of four units with a total installed capacity of 732MW, began in April 2016. The first unit of phase two was commissioned in December 2019, while the remaining units are expected to be commissioned by 2020.
Contract farming
Contract farming
No