Deal #8299
India
Created at
2020-09-13
Last update
2020-12-02
Last full update
2020-11-18
Land area
Size under contract (leased or purchased area)
- [current] 526.0 ha
Size in operation (production)
- [current] 453.99 ha
Comment on land area
Acquired: 526 hectares
Operations: 2361.02 (382.35 hectares) private land and 441.05 Bigha (71.42 hectares) government land; Total - 453.99 hectares
Intention of investment
Intention of investment
- [current] Industry
Comment on intention of investment
Coal-fired Thermal Power Plant
Nature of the deal
Nature of the deal
Outright purchase
Negotiation status
Negotiation status
- [current] Concluded (Contract signed)
- [2017-01-12] Concluded (Change of ownership)
Comment on negotiation status
State-run NTPC has signed a non-binding agreement with Rajasthan Rajya Vidyut Utpadan Nigam Ltd and Rajasthan Urja Vikas Nigam Ltd to take over Chhabra Thermal Power Plant. (according to a media report in 2017)
Implementation status
Implementation status
- [2010-06-11, current] In operation (production)
Comment on implementation status
Operational with Stage III under construction.
Contract farming
Contract farming
No