Deal #7570

Brazil
Created at
2019-12-17
Last update
2024-04-19
Last full update
2024-04-19

Land area

Size under contract (leased or purchased area)
  • [2011, current] 10424 ha
Size in operation (production)
  • [2017, current] 10424 ha

Intention of investment

Intention of investment
  • [2011, current] Wind farm (10424 ha)

Nature of the deal

Nature of the deal
Lease

Negotiation status

Negotiation status
  • [2011] Concluded (Contract signed)
  • [2019, current] Concluded (Change of ownership)
Comment on negotiation status
The previous version of this deal indicated that the contract was signed in 2016. However, some data sources show that the company leased the properties in 2011.

Implementation status

Implementation status
  • [2017] In operation (production)
  • [2024, current] In operation (production)
Comment on implementation status
The project is still in operation in 2024.