Deal #7432
Burkina Faso
Created at
2019-11-18
Last update
2021-06-14
Last full update
2021-05-25
Land area
Intended size
2 960 ha
Size under contract (leased or purchased area)
- [2017, current] 2960.0 ha
Intention of investment
Intention of investment
- [current] Mining
Comment on intention of investment
Open Pit/Contractor mining
Nature of the deal
Nature of the deal
Exploitation permit / license / concession (for mineral resources)
Negotiation status
Negotiation status
- [2016-12, current] Concluded (Contract signed)
Comment on negotiation status
The project was granted a permit to operate in December 2016. construction took about eighteen months.
Implementation status
Implementation status
- [2018] In operation (production)
- [2019] Startup phase (no production)
- [2020, current] In operation (production)
Comment on implementation status
In 2018, the mine was in operation. However, November 2019, following the deadly attack on its employees, operations at the mine were suspended. Mining activities recommenced in Q4 2020.
Contract farming
Contract farming
No