Please note: you are viewing an old version of this deal. The current version can be found here: Deal #6620

Deal #6620 Version #76373

Ghana
Created at
2018-11-26
Last update
2018-11-26
Last full update
2024-02-22

Land area

Size under contract (leased or purchased area)
  • [current] 3000.0 ha

Intention of investment

Intention of investment
  • [current] Industry
Comment on intention of investment
Sugarcane factory

Negotiation status

Negotiation status
  • [current] Concluded (Contract signed)

Implementation status

Implementation status
  • [2016] Startup phase (no production)
  • [current] Project not started
Comment on implementation status
Factory was opened in 2016, now project is on hold due to lack of raw material to feed the factory and financial issues. Project not abandoned, investors are trying to revive it.

Contract farming

Contract farming
Yes
Not on leased / purchased (out-grower)
Yes
Not on leased area/farmers/households (out-grower)
  • [current] 7500