Deal #6606 Version #76322
Lao PDR
Created at
2015-12-07
Last update
2020-09-07
Last full update
2022-08-17
Land area
Intended size
6 200 ha
Comment on land area
approximate reservoir size is 62 square kilometer
Intention of investment
Intention of investment
- [current] Renewable energy unspecified
Comment on intention of investment
Nam Tha 1 hydropower project, installed capacity: 168MW; the station was built with the goals of power generation with additional services such as flood control and irrigation
Nature of the deal
Nature of the deal
Concession
Negotiation status
Negotiation status
- [2006-01-01] Concluded (Contract signed)
- [2010-01-01] Concluded (Contract signed)
- [2014-11-01, current] Concluded (Contract signed)
- [1990-01-01] Intended (Expression of interest)
Comment on negotiation status
The Nam Tha 1 project has been under consideration since the early 1990s, but was previously regarded as a low priority for development due to high costs and low potential returns on investment. Memorandum of Understanding (MoU) signed in 2006, Project Development Agreement (PDA) signed in 2010, Concession Agreement (CA) signed in November 2014
Implementation status
Implementation status
- [2014-01-01] Startup phase (no production)
- [2015-01-01] Startup phase (no production)
- [2019-04-01, current] In operation (production)
Comment on implementation status
Operation was expected to start in 2012 but was delayed. River diversion was done in 2015. The dam’s three generators were put into operation on October 26, 2018 and the recent document issued by the Ministry of Energy and Mines of Laos marked the COD of Nam Tha 1 Hydropower Station on April 1, 2019.