2022-08-17

Land area

Intended size
7 620 ha
Size under contract (leased or purchased area)
  • [2006-12-01, current] 7640.0 ha

Intention of investment

Intention of investment
  • [current] Mining, Industry
Comment on intention of investment
Coal thermal power plant and Lignite mining project, installed capacity: 1878 MW

Nature of the deal

Nature of the deal
Concession
Comment on nature of the deal
Operation and Maintenance Agreement

Negotiation status

Negotiation status
  • [current] Concluded (Contract signed)

Implementation status

Implementation status
  • [2009-10-01] Startup phase (no production)
  • [2015-01-01, current] In operation (production)
Comment on implementation status
2009-10-01:Construction of power plant, water reservoir and pit started in October 2009. 2015-01-01:Two generators (out of three) fully operational as of November 2015