Please note: you are viewing an old version of this deal. The current version can be found here: Deal #6602
Deal #6602 Version #76303
Lao PDR
Created at
2015-12-02
Last update
2020-12-09
Last full update
2022-08-17
Land area
Intended size
7 620 ha
Intention of investment
Intention of investment
- [current] Mining
Comment on intention of investment
Hongsa lignite power plant, installed capacity: 1878 MW
Nature of the deal
Nature of the deal
Lease
Negotiation status
Negotiation status
- [current] Concluded (Contract signed)
Implementation status
Implementation status
- [2014-01-01] Startup phase (no production)
- [2015-01-01, current] In operation (production)
Comment on implementation status
2014-01-01:Construction of power plant, water reservoir and pit started in October 2009.
Generator units will start with electricity generation in 2015
2015-01-01:Two generators (out of three) fully operational as of November 2015