Please note: you are viewing an old version of this deal. The current version can be found here: Deal #6602

Deal #6602 Version #76301

Lao PDR
Created at
2015-12-02
Last update
2020-10-27
Last full update
2022-08-17

Land area

Intended size
7 620 ha

Intention of investment

Intention of investment
  • [current] Mining
Comment on intention of investment
Hongsa lignite power plant, installed capacity: 1878 MW

Nature of the deal

Nature of the deal
Lease

Negotiation status

Negotiation status
  • [current] Concluded (Contract signed)

Implementation status

Implementation status
  • [2014-01-01] Startup phase (no production)
  • [2015-01-01, current] In operation (production)
Comment on implementation status
2014-01-01:Construction of power plant, water reservoir and pit started in October 2009. Generator units will start with electricity generation in 2015 2015-01-01:Two generators (out of three) fully operational as of November 2015