Land area
Intended size
7 620 ha
Intention of investment
Intention of investment
- [current] Mining
Comment on intention of investment
Hongsa lignite power plant, installed capacity: 1878 MW
Nature of the deal
Nature of the deal
Lease
Negotiation status
Negotiation status
- [current] Concluded (Contract signed)
Implementation status
Implementation status
- [2014-01-01] Startup phase (no production)
- [2015-01-01, current] In operation (production)
Comment on implementation status
2014-01-01:Construction of power plant, water reservoir and pit started in October 2009.
Generator units will start with electricity generation in 2015