Please note: you are viewing an old version of this deal. The current version can be found here: Deal #6598
Deal #6598 Version #76283
Lao PDR
Created at
2015-10-29
Last update
2021-04-05
Last full update
2022-09-22
Land area
Size in operation (production)
- [current] 5598.0 ha
Comment on land area
The project will have a total reservoir area of 5,360 hectares. The project was being developed on a 238ha land leased for a period of 32 years.
Intention of investment
Intention of investment
- [current] Renewable energy unspecified
Comment on intention of investment
Xe-Pian Xe-Namnoy hydroelectric scheme, installed capacity: 410 MW, developed by an independent power producer
Nature of the deal
Nature of the deal
Concession
Comment on nature of the deal
PNPC signed a concession agreement for the project with the Lao government in October 2012.
Negotiation status
Negotiation status
- [2012-10-19, current] Concluded (Contract signed)
Comment on negotiation status
Project Development Agreement (PDA) signed on 14/11/2008, Concession Agreement (CA) signed on 19/10/2012
Implementation status
Implementation status
- [2013-01-01, current] Startup phase (no production)
Comment on implementation status
2013: start of construction