Deal #6542
Lao PDR
Created at
2015-01-06
Last update
2022-10-10
Last full update
2022-10-10
Land area
Intended size
0 ha
Intention of investment
Intention of investment
- [current] Renewable energy unspecified
Comment on intention of investment
Xekong 3 hydropower project, installed capacity: 250 MW
[Source: Power Technology ]
Nature of the deal
Nature of the deal
Lease
Negotiation status
Negotiation status
- [2012-07-27, current] Concluded (Contract signed)
Comment on negotiation status
Project Development Agreement (PDA) signed on 27/07/2012
Implementation status
Implementation status
- [2013-05-01, current] Startup phase (no production)
Comment on implementation status
The project got commissioned in 2013 and it was expected to complete by 2015
[Source: Power Technology & Viet Nam Breaking News]
Purchase price
Purchase price
311 730 000
$
Comment on purchase price
The project cost is $311.73 million
[Source: Power Technology]