1. Contract #37XwpFto
Date
1998-01-01
Duration of the agreement
30 years
Comment on contract
Commercial operation started in 1998 under a 30-year BOT “build–operate–transfer” agreement with option for a 10 year extension. After the concession period the plant reverts to the Lao government.