Use of produce
Has export
Yes
Export
100 %
Country 1
Thailand
In country processing of produce
In country processing of produce
Yes
Comment on in country processing of produce
The powerhouse is located on the right bank of Nam Louk (river) and contains two 43 MW Pelton turbines (86 MW total) that send power through a 115-kV transmission line to Thongkhoun II substation. Its projected annual power output is 419 GWh.