Deal #6523 Version #75948
Lao PDR
Created at
2014-12-31
Last update
2020-12-09
Last full update
2022-09-16
Land area
Intended size
0 ha
Comment on land area
The dam will be approximately 39.5m high from its foundations to its crest with overall dam crest length of approximately 148.6m.
Intention of investment
Intention of investment
- [current] Renewable energy unspecified
Comment on intention of investment
Nam Lik 1, installed capactiy: 64.7 MW, developed by an independent power producer (IPP)
Nature of the deal
Nature of the deal
Concession
Comment on nature of the deal
NL1PC signed a concession agreement with the Government of Lao PDR on 6 February 2013 in the form of Build-Own-Operate and Transfer (BOT) to Lao PDR with the duration of 30 years.
Negotiation status
Negotiation status
- [2006-01-01] Intended (Under negotiation)
- [2013-01-01, current] Concluded (Contract signed)
Comment on negotiation status
Memorandum of Understanding (MoU) signed in 2006, Project Development Agreement (PDA) signed on 08/04/2008 and Concession Agreement (CA) signed on 06/02/2013
Implementation status
Implementation status
- [2014-01-01, current] Startup phase (no production)
Comment on implementation status
Dam construction started in June 2014, with commercial operations slated to commence three years later.