Comment on negotiation status | MoEE and SPIC signed the joint venture agreement on 3 June 2010. | |
Implementation status |
|
|
Comment on implementation status | Chipwi HPP was suspended due to armed conflicts in north Myanmar on April 26, 2012. | Chipwi HPP was suspended due to armed conflicts in north Myanmar on April 26, 2012. Listed as Planned hydropower project of SPIC (formerly CPI) (target completion: 2020) in IFC assessment report but no evidence of the project being resumed. |
Employment | ||
Investor info | ||
Actors involved in the negotiation / admission process |
| |
Comment on investment chain | Joint Venture between MoEE and SPIC (formerly CPI). | |
Local communities / indigenous peoples | ||
Presence of land conflicts | Yes | |
Comment on presence of land conflicts | Due to armed conflict, project was halted last 26 April 2012 | |
Negative impacts for local communities | Violence | |
Comment on negative impacts for local communities | Armed conflict | |
Former use | ||
Produce info | ||
Water | ||
Gender-related info | ||
Overall comment | ||
Meta | ||
Fully updated | No | Yes |
Locations | ||
Location #LY7F3qFo | ||
Facility name | Chipwe HPP | |
Comment | Chipwi HPP is the fifth cascade HPP planned on the main stream of the Maykha River. Its dam site is about 150 km from Myitkyina City and about 10 km from Chipwi Village.
The dam site is on the Nβmai River at Mandung village, ten miles from the town of Chibwe, Kachin State | Chipwi HPP is the fifth cascade HPP planned on the main stream of the Maykha River. Its dam site is about 150 km from Myitkyina City and about 10 km from Chipwi Village.
The dam site is on the Nβmai River at Mandung village, ten miles from the town of Chibwe, Kachin State. |
Data sources | ||
Data source #PskK1IaH | ||
Url | ||
Date | 2018-12-17 | 2021-07-06 |
Comment on data source | Accessed on 17 December 2018 | Project details. Updated link and attachment. Accessed 06 July 2021. |
Data source #Vn_Saceb | ||
Date | 2018-12-14 | 2021-07-06 |
Comment on data source | shareholder information; accessed on 17 December 2018 | Shareholder information. Updated attachment. accessed on 06 July 2021. |
Data source #YcTm34BG | ||
Type | Research Paper / Policy Report | |
Url | ||
Keep PDF not public | No | |
Publication title | BASELINE ASSESSMENT REPORT HYDROPOWER: Strategic Environmental Assessment of the Hydropower Sector in Myanmar | |
Date | 2017-01-01 | |
Comment on data source | Chipwi HPP listed as a "planned hydropower project". Expected power generation. Accessed 06 July 2021. | |
Data source #-hpVZWGT | ||
Type | Company sources | |
Url | ||
Keep PDF not public | No | |
Publication title | Statement of ACHC | |
Date | 2016-06-17 | |
Comment on data source | company-issued statement regarding controversy surrounding the project. Accessed 06 July 2021. | |