Please note: you are viewing an old version of this deal. The current version can be found here: Deal #6016

Deal #6016 Version #74665

Myanmar
Created at
2018-04-30
Last update
2018-12-17
Last full update
2022-01-27

Land area

Intended size
2 889 ha
Comment on land area
reservoir area based on GIS calculation, knowing that the reservoir would have a normal pool level of 400 meters above sea level (information given on ACHC Website)

Intention of investment

Intention of investment
  • [current] Renewable energy unspecified
Comment on intention of investment
Hydropower dam

Negotiation status

Negotiation status
  • [2010, current] Concluded (Contract signed)

Implementation status

Implementation status
  • [2010] Startup phase (no production)
  • [2012, current] Project abandoned
Comment on implementation status
Chipwi HPP was suspended due to armed conflicts in north Myanmar on April 26, 2012.