Please note: you are viewing an old version of this deal. The current version can be found here: Deal #5928

Deal #5928 Version #74291

Kenya
Created at
2018-01-26
Last update
2018-01-26
Last full update
2024-11-19

Land area

Comment on land area
size unknown

Intention of investment

Intention of investment
  • [current] Renewable energy unspecified
Comment on intention of investment
Geothermal Power Station

Negotiation status

Negotiation status
  • [current] Concluded (Contract signed)

Implementation status

Implementation status
  • [2000] Project not started
  • [2010, current] In operation (production)
Comment on implementation status
Construction started in 2000.

Contract farming

Contract farming
No