Deal #5820

Myanmar
Created at
2017-11-23
Last update
2021-10-05

Land area

Intended size
40 500 ha
Size under contract (leased or purchased area)
  • [2007, current] 40500.0 ha
Comment on land area
Other sources cite: - 76600 hectares as flood zone (Damming the Irrawaddy Report) - 40500 hectares (Foran et al. 2017 P. 625)

Intention of investment

Intention of investment
  • [2007, current] Renewable energy unspecified
Comment on intention of investment
Hydropower dam

Nature of the deal

Nature of the deal
Lease

Negotiation status

Negotiation status
  • [2007, current] Concluded (Contract signed)

Implementation status

Implementation status
  • [2009] Startup phase (no production)
  • [2011, current] Project abandoned
Comment on implementation status
2006 - MoU signed 2007 - Contract signed 2009 - Beginning of construction work 2011 - 29th of September, Suspension of wok