Côte d'Ivoire
Created at
2017-10-09
Last update
2018-03-15
Last full update
2021-05-27
Land area
Comment on land area
Size of mine unknown.
Intention of investment
Intention of investment
- [current] Mining
Nature of the deal
Nature of the deal
Exploitation permit / license / concession (for mineral resources)
Negotiation status
Negotiation status
- [current] Concluded (Contract signed)
Comment on negotiation status
It is not clear when the mining license was granted. Feasibility study completed 2008.
Implementation status
Implementation status
- [2012] Startup phase (no production)
- [2014, current] In operation (production)
Contract farming
Contract farming
No