Please note: you are viewing an old version of this deal. The current version can be found here: Deal #5689

Deal #5689 Version #73309

Mali
Created at
2017-10-06
Last update
2017-10-06
Last full update
2020-08-07

Land area

Comment on land area
156 km2- it is not clear if this size includes both Tabakoto and Segala Underground Operations.

Intention of investment

Intention of investment
  • [current] Mining
Comment on intention of investment
Gold

Nature of the deal

Nature of the deal
Exploitation permit / license / concession (for mineral resources)

Negotiation status

Negotiation status
  • [2012, current] Concluded (Contract signed)
Comment on negotiation status
Endeavour acquired the mine in 2012

Implementation status

Implementation status
  • [2012, current] In operation (production)
Comment on implementation status
Originally started in 2006 and was operational when Endeavour acquired the mine.

Contract farming

Contract farming
No