Please note: you are viewing an old version of this deal. The current version can be found here: Deal #5430

Deal #5430 Version #91864

Kenya
Created at
2017-04-06
Last update
2024-02-16
Last full update
2024-11-12

Land area

Intended size
7 567 ha
Size under contract (leased or purchased area)
  • [2016, current] 7567 ha
Comment on land area
18,700-acre= 7567.6282

Intention of investment

Intention of investment
  • [2016, current] Wind farm (7567 ha)

Negotiation status

Negotiation status
  • [2016, current] Concluded (Contract signed)

Implementation status

Implementation status
  • [2017] Project not started
  • [2023, current] Project not started
Comment on implementation status
Construction delayed due to land rights disputes and compensation issues with landowners. Construction expected to commence in 2019. The company has been working to resolve these issues and secure financing. The company is still trying to clear these issues (2023). However, Global Energy Monitor Wiki lists the project status as shelved- ''Shelved: Suspension has been announced, or no progress has been observed for at least two years.''

Contract farming

Contract farming
No