Please note: you are viewing an old version of this deal. The current version can be found here: Deal #5259
Deal #5259 Version #71829
Vietnam
Created at
2016-10-05
Last update
2016-10-24
Last full update
2022-03-18
Land area
Size under contract (leased or purchased area)
- [2006, current] 346.0 ha
Comment on land area
Phase 1: 220 ha, (in 2013, occupacy was 90%)
Phase 2: 126 ha, started in 2014 (Vietnamese source: http://khucongnghiep.com.vn/xuctien/tabid/67/articleType/ArticleView/articleId/851/KCN-Thng-Long-II--im-n-ca-cc-nh-u-t.aspx)
Intention of investment
Intention of investment
- [current] Industry
Nature of the deal
Nature of the deal
Lease
Negotiation status
Negotiation status
- [2006, current] Concluded (Contract signed)
Implementation status
Implementation status
- [2014, current] In operation (production)
Comment on implementation status
In operation since 2009, establishment in 2006. The most update information is in 2016.
Contract farming
Contract farming
No