Intention of investment

Intention of investment
  • [2009, current] Mining
Comment on intention of investment
Mining and leaching project comprising the Muliashi North Mine and the Muliashi Leach Plant

Nature of the deal

Nature of the deal
Exploitation permit / license / concession (for mineral resources)

Negotiation status

Negotiation status
  • [2009, current] Concluded (Contract signed)
Comment on negotiation status
CNMC acquired a stake in Luanshya Copper Mines in 2009 for US$ 50 million from Enya Holdings BV of the United Kingdom.

Implementation status

Implementation status
  • [2010] Startup phase (no production)
  • [2012, current] In operation (production)
Comment on implementation status
The construction of the Muliashi Project was initiated in 2010 with production commencing in 2012.

Contract farming

Contract farming
No