Deal #5128
Zambia
Created at
2016-07-21
Last update
2021-12-14
Last full update
2017-01-27
Land area
Comment on land area
Size is not known.
Intention of investment
Intention of investment
- [2009, current] Mining
Comment on intention of investment
Mining and leaching project comprising the Muliashi North Mine and the Muliashi Leach Plant
Nature of the deal
Nature of the deal
Exploitation permit / license / concession (for mineral resources)
Negotiation status
Negotiation status
- [2009, current] Concluded (Contract signed)
Comment on negotiation status
CNMC acquired a stake in Luanshya Copper Mines in 2009 for US$ 50 million from Enya Holdings BV of the United Kingdom.
Implementation status
Implementation status
- [2010] Startup phase (no production)
- [2012, current] In operation (production)
Comment on implementation status
The construction of the Muliashi Project was initiated in 2010 with production commencing in 2012.
Contract farming
Contract farming
No