Mining and leaching project comprising the Muliashi North Mine and the Muliashi Leach Plant
Nature of the deal
Nature of the deal
Exploitation permit / license / concession (for mineral resources)
Negotiation status
Negotiation status
- [2009, current] Concluded (Contract signed)
Comment on negotiation status
CNMC acquired a stake in Luanshya Copper Mines in 2009 for US$ 50 million from Enya Holdings BV.
Implementation status
Implementation status
- [2010] Startup phase (no production)
- [2012, current] In operation (production)
Comment on implementation status
The construction of the Muliashi Project was initiated in 2010 with production commencing in 2012.