Please note: you are viewing an old version of this deal. The current version can be found here: Deal #4953
Deal #4953 Version #70265
Guinea
Created at
2016-01-27
Last update
2019-04-09
Last full update
2017-01-12
Land area
Intended size
160 000 ha
Size under contract (leased or purchased area)
- [2010, current] 160000.0 ha
Comment on land area
Lefa gold mine operates a typical modern open pit operation with three major mining areas and several smaller, higher grade satellite pits.
Intention of investment
Intention of investment
- [current] Mining
Negotiation status
Negotiation status
- [2010, current] Concluded (Contract signed)
Comment on negotiation status
The mine was acquired by Nordgold at the end of July 2010
Implementation status
Implementation status
- [2010, current] In operation (production)
Comment on implementation status
Commercial production began at the Lefa mine in 2008 (with previous owner).
Contract farming
Contract farming
No