Please note: you are viewing an old version of this deal. The current version can be found here: Deal #4767
Deal #4767 Version #69330
Liberia
Created at
2015-09-10
Last update
2015-09-10
Last full update
2017-10-05
Land area
Intended size
45 700 ha
Size under contract (leased or purchased area)
- [2009, current] 45700.0 ha
Intention of investment
Intention of investment
- [current] Mining
Nature of the deal
Nature of the deal
Exploitation permit / license / concession (for mineral resources)
Comment on nature of the deal
Class A mining license was granted in 2009. New Liberty is expected to have an eight-year life.
Negotiation status
Negotiation status
- [2009, current] Concluded (Contract signed)
Comment on negotiation status
Exploration license was granted in 1996. Class A mining license was granted in 2009. Preliminary economic assessment (PEA) was filed in 2010. Definitive Feasibility Study was completed in 2013.
Implementation status
Implementation status
- [2009] Startup phase (no production)
- [2015, current] In operation (production)
Comment on implementation status
Feasibility stage has been completed and the company is now in the construction phase.
Contract farming
Contract farming
No