Deal #3380 Version 60465 Version 86092
Size under contract (leased or purchased area)
  • [2010, current] 70000.0 ha
  • [2010, current] 70000 ha
Comment on implementation status
Project has been temporarily abandoned/halted, since parts of the concession are located in areas that are “sensitive to the national security and defense” (http://www.vir.com.vn/forest-projects-facing-the-axe.html).
Project has been temporarily abandoned/halted, since parts of the concession are located in areas that are “sensitive to the national security and defense” (http://www.vir.com.vn/forest-projects-facing-the-axe.html). In Que Phong district, the company only planted about 1/3 of the leased land, then stopped, neglected until now. Plants are not cared for and protected, so the survival rate is very low. According to a recent report by the People's Committee of Que Phong district, InnovGreen Co., Ltd. has only planted 294 hectares and from 2011-2019 until now has not planted any more trees. see: https://thanhnien.vn/du-an-trong-rung-cua-innovgreen-hien-ra-sao-post852725.html On March 5, 2019, H.Que Phong People's Committee issued a written report on the results of reviewing projects in the area behind schedule, including the project of InnovGreen Nghe An Company.
Comment on community reaction
Investors have not kept their word, local people lost land, jobs and have to go to streams to sift for gold (http://en.baomoi.com/Info/What-is-InnovGreen-doing-on-Vietnams-border/3/85931.epi)
Investors have not kept their word, local people lost land, jobs and have to go to streams to sift for gold (http://en.baomoi.com/Info/What-is-InnovGreen-doing-on-Vietnams-border/3/85931.epi) Regarding the meetings to get people's opinions on the project implementation, people in the district did not agree to lease land to the company for afforestation, but the company continued to implement it because it was licensed by the Provincial People's Committee. see: https://thanhnien.vn/du-an-trong-rung-cua-innovgreen-hien-ra-sao-post852725.html
Negative impacts for local communities
Socio-economic
Comment on negative impacts for local communities
In Huoi May village, people are sandwiched between the Pu Hoat nature reserve and the land of InnovGreen. “After InnovGreen implemented the project, people were not allowed to let their buffaloes and cows roam freely, so it became more and more difficult for them. The commune has requested many times to recover the land and return it to the people, but it has not been accepted. In Nam Nhoong commune, 80 households of Na Khich and Pu Lau villages are also "hungry" for forest land, while the land allocated to InnovGreen Nghe An Company for the past 10 years has not yielded any results. In Pu Lau village, after being allocated land, InnovGreen Nghe An Company was allowed to plant acacia, but as noted by the reporter, this area is now mainly shrubs, only a few scattered acacia trees remain. see: https://thanhnien.vn/du-an-trong-rung-cua-innovgreen-hien-ra-sao-post852725.html
Fully updated
No
Yes

Data source #3jomhVbQ

Url
Publication title
Phải dừng nếu ảnh hưởng đến quốc phòng
Date
2015-03-15
Comment on data source
Information on leasing price. Broken link
Information on leasing price.

Data source #O3Lk_R7O

File
Type
Media report
Url
Keep PDF not public
No
Publication title
Dự án trồng rừng của InnovGreen hiện ra sao?
Date
2019-05-24
Comment on data source
Provides info on local people reaction, implementation status, negative impact on local communities