Please note: you are viewing an old version of this deal. The current version can be found here: Deal #3129

Deal #3129 Version #58901

Peru
Created at
2013-02-25
Last update
2018-03-15
Last full update
2019-07-29

Land area

Size under contract (leased or purchased area)
  • [2013, current] 7400.0 ha

Intention of investment

Intention of investment
  • [current] Mining

Nature of the deal

Nature of the deal
Lease, Exploitation permit / license / concession (for mineral resources)

Negotiation status

Negotiation status
  • [2005, current] Concluded (Contract signed)
Comment on negotiation status
In 2005, Rio Tinto won the public tender called by the Peruvian government, to explore and analyze the possibility of developing the mining concession. On January 31, 2006 signed the concession contract and based Rio Tinto Minera Peru SAC Limited (Rio Tinto-La Granja) Project Management, a company owned by Rio Tinto 100%.

Implementation status

Implementation status
  • [2013, current] Startup phase (no production)

Contract farming

Contract farming
No