Deal #1132
Côte d'Ivoire
Created at
2013-02-15
Last update
2017-01-10
Last full update
2017-01-10
Land area
Comment on land area
Land Area information unknown.
Intention of investment
Intention of investment
- [current] Mining
Nature of the deal
Nature of the deal
Exploitation permit / license / concession (for mineral resources)
Negotiation status
Negotiation status
- [2008, current] Concluded (Contract signed)
Comment on negotiation status
1996- Niellé Exploration Permit acquired in November.
2008- Completion of the review of pre feasibility study in February.
2008- Approval of the Feasibility Plan by the Board of Directors in May. Another source states that the contract was signed in 2010.
Implementation status
Implementation status
- [2008] Project not started
- [2010, current] In operation (production)
Comment on implementation status
2008-Start of Tongon site earth works10-year lifespan.
2009-Mining activities started in November. 2010- First gold , December.
Contract farming
Contract farming
No