Deal #11034

Philippines
Created at
2024-12-13
Last update
2025-01-07
Last full update
2025-01-07

Detailed electricity generation information

Electricity generation
  • [2024, current] Solar (Photovoltaic) 3 500 ha
    Intended capacity: 3 500 MW
Comment on electricity generation
Project is still currently under construction (started in 2024) and is expected to be fully operational by 2027

Detailed carbon sequestration/offsetting information

Carbon sequestration/offsetting
  • [2027, current] Solar park ( 3 500 ha)
    Estimated annual emission reduction/removal: 4 300 000 tCO2e
    Certification standard: No
Comment on carbon sequestration/offsetting
the project would energize over two million households and reduce carbon emissions by more than 4.3 million metric tons annually.

Use of produce

Has domestic use
Yes
Domestic use
100 %
Has export
No