Deal #10989
Cambodia
Created at
2024-12-01
Last update
2025-01-21
Last full update
2025-01-21
Land area
Intended size
5 098.67 ha
Size under contract (leased or purchased area)
- [2012-11-03, current] 4 674 ha
Size in operation (production)
- [2013, current] 4 674 ha
Comment on land area
Intended size is based on the EIA report
Size under contract and operation are Based on the sub decree document
Intention of investment
Intention of investment
- [2012-11-03, current] Renewable energy unspecified (4 674 ha)
Carbon offset project
Carbon offset project
Yes
Comment on carbon offset project
Listed as Project 8903 : Cambodia Stung Atay Hydropower Project under the UNFCCC-CDM
Nature of the deal
Nature of the deal
Concession
Comment on nature of the deal
The dam project began construction in 2008 and completed last year under a 34-year concessional contract of build-operate-transfer (BOT) with the Cambodian government, he said.
Negotiation status
Negotiation status
- [2012-11-03, current] Concluded (Contract signed)
Comment on negotiation status
Date contract was issued
Implementation status
Implementation status
- [2008] Startup phase (no production)
- [2013, current] In operation (production)
Comment on implementation status
Construction began in 2008 and the plant became operational in 2013
Contract farming
Contract farming
No