Deal #10894
Philippines
Created at
2024-11-03
Last update
2025-01-21
Last full update
2025-01-21
Land area
Intended size
26 ha
Size under contract (leased or purchased area)
- [current] 26 ha
Size in operation (production)
- [2014-10, current] 11.96 ha
Comment on land area
Phase 1 and Phase 2 were supposed to run along 9km of the shore. Nevertheless, Phase 3 was completed in 2014 and the full extend of the project was not announced. However, we looked at the images on google maps an mapped that all of the windmills cover an area of 26ha in total, meanwhile individually they cover 11.96ha.
Intention of investment
Intention of investment
- [2005-05-07, current] Wind farm
Comment on intention of investment
The wind farm was developed in 3 phases. Phase 1 was completed on 2005 and consisted of 15 wind turbines. Then, In 2008, during Phase II, 5 more wind turbines were added. Finally in 2014, during Phase III, 6 more turbines were added.
Turbined from Phase I & II have a capacity of 1.65 MW, and turbines of Phase III have a capacity of 3MW, making the wind firm with a total capacity of 51MW.
Sources: www.acenrenewables.com, manilastandard.net & .pressreader.com
Carbon offset project
Carbon offset project
Yes
Comment on carbon offset project
Its construction was not necessarily intended for only carbon offset but it is reported that its intention was for "sustainable economic development through the enhancement of both quantity and reliability of power supply in an environmentally sustainable manner. The Project will also contribute towards the global environment objective of reducing greenhouse gas emissions through the avoidance of thermal power generation."
Also, although it is not necessarily a carbon offset project it must be informed that "Northwind earned carbon credits from the project — and will sell $1.5 million worth of them over 10 years to the World Bank which manages a carbon credit fund as part of the Kyoto protocol to reduce greenhouse gases".
Source: projects.worldbank.org & www.philstar.com
Nature of the deal
Nature of the deal
Concession
Comment on nature of the deal
Purpose of the project was to contribute to the country's development objectives of sustainable economic development through the enhancement of both quantity and reliability of power supply in an environmentally responsible manner.
Source: projects.worldbank.org
Negotiation status
Negotiation status
- [1996] Concluded (Contract signed)
- [2004-04] Concluded (Contract signed)
- [2017, current] Concluded (Change of ownership)
Comment on negotiation status
In 1996, the National Renewable Energy Laboratory (NREL) conducted a wind resource analysis and mapping study, including in the areas of Ilocos Norte.
Project design document form (PDF) stated that the contract was signed in 2004
AC Energy, the listed energy platform of the Ayala Group, eventually took control of Northwind and of the Bangui Wind Farm in 2017, acquiring a total of 67.79% of Northwind stocks.
Implementation status
Implementation status
- [2005-05-07] In operation (production)
- [2008] In operation (production)
- [2014-10, current] In operation (production)
Comment on implementation status
Each date refers to each phase of the project.
Purchase price
Purchase price
35 450 000
$
Comment on purchase price
This is the total cost for phase I and II. There is no information on Phase III.
Source: projects.worldbank.org