Deal #10866
Philippines
Created at
2024-10-27
Last update
2025-01-21
Last full update
2025-01-21
Detailed electricity generation information
Electricity generation
- [2023, current] On-shore wind turbines
Number of turbines: 32 Currently installed capacity: 80 MW Intended capacity: 160 MW
Comment on electricity generation
The project will feature 32 wind turbines with a generation of 5 MW each from wind turbine supplier Siemens Gamesa.
According to ACEN's project profile page, as of 2023 phase 1 (80mw) has been in operation and phase 2 (80MW) is under construction
Detailed carbon sequestration/offsetting information
Carbon sequestration/offsetting
- [2023-12-25–2028-12-24, current] Wind farm Estimated annual emission reduction/removal: 19 500 tCO2eProject proponents: Bayog Wind Power Corp.Certification standard: YesName of certification standard/mechanism: Gold Standard for the Global Goals (GOLD)ID of certification standard/mechanism: 11423: 160MW Balaoi & Caunayan Wind Energy Project
Comment on carbon sequestration/offsetting
Length of the project and project proponents remains unknown. The only thing known is the amount of CO2 that is displaced annually.
Source: malaya.com.ph & cleantech.ph