Deal #10811
South Africa
Created at
2024-10-15
Last update
2024-10-16
Land area
Intended size
168 ha
Size under contract (leased or purchased area)
- [current] 168 ha
Intention of investment
Intention of investment
- [current] Solar park (168 ha)
Comment on intention of investment
Solar energy production
Carbon offset project
Carbon offset project
No
Nature of the deal
Nature of the deal
Lease
Negotiation status
Negotiation status
- [current] Concluded (Contract signed)
Implementation status
Implementation status
- [2019-11] Startup phase (no production)
- [2021-04, current] In operation (production)
Comment on implementation status
The solar project achieved commercial operation in April 2021, less than 18 months after construction commenced, in November 2019.