Deal #10805
South Africa
Created at
2024-10-14
Last update
2024-10-15
Land area
Intended size
330 ha
Size under contract (leased or purchased area)
- [current] 185 ha
Comment on land area
Stands on 185 hectares of agricultural land.
Intention of investment
Intention of investment
- [2016, current] Solar park (184.95 ha)
Carbon offset project
Carbon offset project
No
Nature of the deal
Nature of the deal
Lease
Negotiation status
Negotiation status
- [current] Concluded (Contract signed)
Implementation status
Implementation status
- [2019] Startup phase (no production)
- [2021, current] In operation (production)
Comment on implementation status
Commercial operation date is 23 January 2021, less than two years after construction commenced, in March 2019.