Deal #10805

South Africa
Created at
2024-10-14
Last update
2024-10-15

Land area

Intended size
330 ha
Size under contract (leased or purchased area)
  • [current] 185 ha
Comment on land area
Stands on 185 hectares of agricultural land.

Intention of investment

Intention of investment
  • [2016, current] Solar park (184.95 ha)

Carbon offset project

Carbon offset project
No

Nature of the deal

Nature of the deal
Lease

Negotiation status

Negotiation status
  • [current] Concluded (Contract signed)

Implementation status

Implementation status
  • [2019] Startup phase (no production)
  • [2021, current] In operation (production)
Comment on implementation status
Commercial operation date is 23 January 2021, less than two years after construction commenced, in March 2019.