Deal #10739
Vietnam
Created at
2024-09-30
Last update
2025-01-27
Last full update
2025-01-27
Detailed electricity generation information
Electricity generation
- [current] Solar (Photovoltaic) 270.2 ha
Currently installed capacity: 240 MW Intended capacity: 240 MW
Detailed carbon sequestration/offsetting information
Carbon sequestration/offsetting
- [2019-06-13–2029-06-12, current] Solar park ( 270.2 ha) Estimated emission reduction/removal during project lifetime: 3 322 023 tCO2eEstimated annual emission reduction/removal: 332 202 tCO2eProject proponents: Dau Tieng Tay Ninh Energy Joint Stock Company (DTE)Certification standard: YesName of certification standard/mechanism: OtherID of certification standard/mechanism: S00619Comment on certification standard / mechanism: Registered in Global Carbon Council