Detailed electricity generation information
Electricity generation
- [2014, current] On-shore wind turbines
Number of turbines: 27 Currently installed capacity: 54 MW
Detailed carbon sequestration/offsetting information
Carbon sequestration/offsetting
- [2014-07-01–2024-06-30, current] Wind farm Estimated emission reduction/removal during project lifetime: 654 680 tCO2eEstimated annual emission reduction/removal: 65 468 tCO2eCertification standard: YesName of certification standard/mechanism: Clean Development Mechanism (CDM)ID of certification standard/mechanism: Project 8285 : San Lorenzo Guimaras 54 MW Wind Power Project
Comment on carbon sequestration/offsetting
Irish company ESBI Contracting Ltd was involved orignally but withdrew in 2012-12-26, which renewed the crediting period
Use of produce
Has domestic use
Yes
Domestic use
100 %
Has export
No
Comment on use of produce
The first wind farm in the Visayas region, the 54 MW Guimaras Wind Farm generates over 120 gigawatt-hours of electricity annually, which can sustain the energy demand of over 48,000 households