Deal #10573

Philippines
Created at
2024-08-29
Last update
2024-10-18
Last full update
2024-10-18

Land area

Size in operation (production)
  • [2016-02, current] 49.18 ha
Comment on land area
Size in operation is basedon the polygon produced via RS

Intention of investment

Intention of investment
  • [2016-03-11, current] Solar park (49.18 ha)
Comment on intention of investment
18MW solar farm

Carbon offset project

Carbon offset project
No

Nature of the deal

Nature of the deal
Concession

Negotiation status

Negotiation status
  • [2015, current] Concluded (Contract signed)
Comment on negotiation status
\

Implementation status

Implementation status
  • [2015-12] Startup phase (no production)
  • [2016-02, current] In operation (production)
Comment on implementation status
As the first solar farm in Negros Oriental, MonteSol was installed in just over 2.5 months or 80 days from “first pile in” to commissioning and energization (“first power out”).

Contract farming

Contract farming
No